PVC System Is the Answer for U.S. Bank Stadium Roof

U.S. Bank Stadium is topped with a PVC roof system that display’s the company’s logo. Photo: Johns Manville

When discussions began about the new U.S. Bank Stadium in Minneapolis, Minnesota, there was a request for an outdoor stadium. However, state and local government provided funding specifically for an indoor stadium that would be able to host major events like the professional football championship game and the college basketball championship game. As a result, a translucent roof and mobile front windows were designed to allow natural light to enter the stadium and to give fans a view of downtown Minneapolis. The mobile windows also allow fans to experience outdoor elements while providing protection from snow, rain and cold winter weather. The roof design was developed taking into consideration the budget and the region’s weather; it would be costly to make it retractable, and a sloped roof lends to a more secure option for snowy weather.

Challenging Task

Berwald Roofing Company Inc., headquartered in North St. Paul, Minnesota, installed an adhered PVC roof system manufactured by Johns Manville over the structure’s metal deck. In all, 280,000 square feet of grey 60-mil PVC were installed. The system also included a vapor barrier and two layers of 1.6-inch ENRGY 3, a rigid roof insulation board composed of a closed-cell polyisocyanurate foam core with fiberglass reinforced facers. Half-inch DensDeck Prime cover board from Georgia-Pacific was also installed.

The roofing portion of the project began in April 2015, with an aggressive completion deadline of November 1, 2015. The schedule and logistics on the project posed major hurdles. “Getting material 300 feet up to the roof was our biggest challenge,” says Berwald Roofing Senior Project Manager Steven Hegge. “A big part of that was scheduling time to share the cranes with the iron workers and general contractor.”

Another challenge was storing material during the installation due to the limited amount of space on the roof. “All the decking had to be installed as we went along, just before roof installation,” Hegge states. “We were on a very tight time schedule in this multiple-phase construction project.”

“The general contractor and Berwald Roofing have worked with Johns Manville on numerous stadium projects in the past and preferred to use JM PVC on this complicated stadium project,” notes Johns Manville sales rep Bob Deans. “This application is on a 3.75-inch to 12-inch slope on the north side of the building, which adds to the difficulty of installing a fully adhered PVC roof assembly.”

The Solution

Due to restricted loading space at the jobsite, materials arrived to Berwald’s yard directly from the manufacturer. They were then loaded on Berwald Roofing semi-trucks each day for delivery. Once they arrived at the site, they were immediately lifted to the roof via tower cranes and installed in the most efficient time frame, to meet the owners expected installation timeline.

The stadium seats approximately 65,000 people for most games. However, this space is built to be expandable to hold up to 73,000 attendees for special events such as the professional football championship game, which the stadium is scheduled to host on February 4, 2018, and for events like the college basketball championship game, which will be held there in 2019. U.S. Bank’s logo is prominently displayed on the rooftop. Charcoal grey 60-mil PVC membrane was cut to specification using a computerized cutter to create an exact replica of the U.S. Bank logo. Berwald Roofing then adhered the charcoal grey PVC on top of the grey 60 mil PVC membrane using JM PVC low-VOC membrane adhesive and then heat-welded the edges of material to finish the application of the logo.

TEAM

Architects: HKS Inc., www.hksinc.com; Studio Hive, www.studiohive.com; Studio Five; and Lawal Scott Erickson Architects Inc., http://lse-architects.com
General Contractor: Mortenson Construction, Minneapolis, Minnesota, www.mortenson.com
Roofing Contractor: Berwald Roofing Company Inc., North St. Paul, Minnesota, https://berwaldroofing.com

MATERIALS

Roof System: 60-mil PVC, Johns Manville, www.jm.com/roofing
Vapor Barrier: Johns Manville
Insulation: ENRGY 3® Insulation, Johns Manville
Cover Board: DensDeck Prime, Georgia-Pacific, www.gp.com

Historic Fleur du Lac Estates Gets New Synthetic Shake Roof

Fleur du Lac Estates is now a private condominium development located on the shore of Lake Tahoe. The Yacht Club and Boat House were the first structures to be re-roofed with synthetic shake. DaVinci Roofscapes

A prime filming location for the 1974 movie “Godfather II,” historic Fleur du Lac Estates in California is now a private condominium development located on the beautiful west shore of Lake Tahoe. A Yacht Club and Boat House, 22 individual homeowner units and a variety of shared recreational facilities make the historic 1938 compound a much-sought-after retreat.

Years of harsh weather conditions had taken their toll on the real cedar shake roofs at Fleur du Lac Estates. Damage from repeated leaks, hail, ice dam issues, snow and other weather conditions recently convinced the board of directors it was time to invest in new roofs for the entire estate.

Homeowners at Fleur du Lac Estates looked for a product that would mimic the look of cedar, but bring them advantages to protect their homes and buildings from Mother Nature. After a comprehensive search, they determined that the Class A fire and Class 4 impact ratings of Bellaforté polymer shake tiles from DaVinci Roofscapes met their needs.

“We started with our two most valuable community structures, the Yacht Club and Boat House,” says Stewart Dalie, maintenance supervisor and project manager at Fleur du Lac Estates in Homewood, California. “Our plans are to re-roof all of the buildings in the Tahoe Blend over the next five to seven years. We did a tremendous amount of research to determine what roofing products would look realistic in this setting, meet the new codes required for roofs in our area, yet offer us superior qualities and a long lifespan.”

“Selecting the fire- and impact-resistant Bellaforté shake material from DaVinci Roofscapes means we won’t have to be concerned with the potential spread of flames should our area ever be touched by wildfires,” Dalie continues. “That’s a huge concern for our geographic area. However, not having to worry about wind-blown embers landing on a roof and then catching the building on fire is a tremendous relief.”

The Class A fire and Class 4 impact ratings of the Bellaforté tiles bring peace-of-mind to residents within the community. The durable roofing tiles have the appearance of natural hand-split cedar shake with slanted sawn edges and staggered lengths, but with the hassle-free qualities of a manufactured product. At a 1-inch average tile thickness, Bellaforté Shake roofing tiles remind many residents of jumbo cedar shakes prevalent in the Lake Tahoe area.

Safeguarding a Historic Setting

It’s not surprising that homeowners at the upscale Fleur du Lac Estates want to invest in the best possible roofing material. This is a mountain and lakeside homeowners association where every home has a deeded slip in the marina, resort-style services are the norm and aesthetics of the community are vigilantly upheld.

Owners chose the Bellaforté polymer shake tiles from DaVinci Roofscapes, which offered Class A fire and Class 4 impact ratings. Photos: DaVinci Roofscapes

Originally the summer home of famous industrialist Henry J. Kaiser, the 15-acre lakeshore site was constructed beginning in 1938. After Kaiser sold the estate, it went through a series of transitional uses from the 1960s to 1979, including serving as a private school and as the site for many on-location scenes for Francis Ford Coppola’s film, “The Godfather II.” Only in the 1980s did the current project begin to refurbish existing key structures and transform original homes on the property to individually-owned homes.

“Our community has always embraced the history of this setting while looking toward protecting its future,” says Lane Murray, general manager at Fleur du Lac Estates. “That’s one of the key reasons we wanted a roofing product that has the look of real cedar shakes, but with man-made advantages like resistance to fire, impact and high winds.”

Despite a variety of challenges with removing the old roofs and prepping for the new synthetic shake tiles, the team at Bruce Olson Construction has successfully tackled their first DaVinci Roofscapes installation project at Fleur du Lac Estates.

“The roofing surface for the Yacht Club and Boat House were in bad shape and very uneven,” says Taylor Greene, general manager of Bruce Olson Construction in Tahoe City, California. “We had to plane these into workable surfaces before getting started. Once we got started the product installed beautifully. We added flashing material to cover some valley locations which made the project look exceptional. To achieve the realistic look, gable end flashing that concealed the manufactured edge of the DaVinci product was added.”

The company, which does residential and multi-family new construction work in several states including Hawaii, has already started work on several additional roofs in the Fleur du Lac complex.

“The Bellaforté roofing looks amazing,” says Greene. “Best of all, these polymer shakes are perfect for this geographic area. Traditional wood shakes ‘hold’ the water from melting snow. Those saturated shakes weigh more and cause the freeze line to be a part of the shake. With the DaVinci product, the water is not absorbed into the tile, so snow melting is faster and more efficient. This can also help reduce the ice damming effect in many locations.”

Laughing at Mother Nature

Nestled amidst stunning mountain peaks and world-famous ski conditions, Fleur du Lac Estates can experience heavy snowfall during the winter months. The property is just five minutes from Homewood Mountain Ski Resort, and the area usually sees snow in excess of 180 inches total. That’s one reason why the community decided to have the Bruce Olson team incorporate snow fences and snow guards from Rocky Mountain Snow Guards into the structures.

Photos: DaVinci Roofscapes

“In our area, it’s very common to use snow guards and fences to help keep snow from falling on individuals and property,” says Greene. “The previous structures at Fleur du Lac Estates didn’t have any type of snow retention system. We believe having these products in place now — which were very simple to put in during the polymer shake installation — will make life much easier for property owners no matter how much snow Mother Nature delivers each season.”

Rocky Mountain Snow Guards custom designed the snow retention system for Fleur du Lac Estates incorporating both their Drift III+ snow fences and the company’s Rocky Guard RG10 snow guards. The system was developed to handle the 180 PSF snow load that can occur in this geographic location.

“The snow guards are attached in a pattern above the snow fence that creates friction to hold the snow slab in place while the snow fence provides a barrier beyond which the snow slab won’t slide,” says Lars Walberg, president of Rocky Mountain Snow Guards. “Using the combination of snow guards and snow fences gives this project a balanced snow retention system that has the look the owners desired.”

For homeowners, the new Bellaforté roofs on the Yacht Club and Boat House are tempting reminders of what will come on their own homes within the community in the years to come.

“Now that the Yacht Club and Boat House roofs are complete, we’re hearing very positive comments from our residents,” says Murray. “Folks are eager for the work to continue in the common areas so that their individual homes can soon get these terrific-looking new roofs.”

Metal Roof and Wall Panels Capture the Spirit of Shakespearean Theater

The Otto M. Budig Theater is the home of the Cincinnati Shakespeare Company. The new theater was designed by GBBN Architects in Cincinnati. Photos: Petersen Aluminum Corp

For many new arenas and theaters, the sheer size and scope of the project can pose the biggest hurdles. At the new Otto M. Budig Theater, home of the Cincinnati Shakespeare Company, the problem was the reverse. The intimate theater was shoehorned into an existing space up against an adjacent building, so logistics were tight. But that didn’t mean the roof system couldn’t be striking. Designed by GBBN Architects in Cincinnati, the building’s exterior features daring angles and multi-colored metal roof and wall panels that combine to help capture the spirit of the Shakespearean theater.

Matt Gennett, senior project manager and vice president of Tecta America Zero Company in Cincinnati, oversaw the roofing portion of the new construction project in the Over the Rhine section of Cincinnati on the corner of Elm Street and 12th Street. “This building was plugged in downtown, and they fit everything in real tight,” he says.

Approximately 5,400 square feet of PAC-CLAD 7/8-inch, 24-gauge Corrugated Panels from Petersen Aluminum Corp. were installed on the metal roofs and walls. Tecta America Zero Company installed the metal roof systems, as well as a TPO roof manufactured by Carlisle SynTec over the main structure and mechanical well. Work began in January of 2017 and the roofing portion of the project was wrapped up in late August.

The Metal Roof System

The building features two different metal roof systems. The roof on the Elm Street side is comprised of three intersecting triangle-shaped sections in two colors, Champagne Metallic and Custom Metallic Bronze. “There were several unique angles on the roof,” Gennett explains. “On the top, there was a second metal roof, a shed roof that went down to the 12th Street side.”

The theater’s roof and walls feature approximately 5,400 square feet of PAC-CLAD 7/8-inch Corrugated Panels from Petersen Aluminum Corp. in two colors. The wall panels are perforated. Photos: Petersen Aluminum Corp.

The metal roof systems were installed over a 2-inch layer of polyisocyanurate insulation and a 2-1/2-inch nail base from Hunter Panels, H-Shield NB. The nail base is a composite panel with a closed-cell polyisocyanurate foam core, a fiber-reinforced facer on one side and, in this case, 7⁄16-inch oriented strand board (OSB) on the other. The nail base was topped with Carlisle WIP 300 HT waterproofing underlayment to dry in the roof.

Crews also installed two rows of snow guards on the metal roof using the S-5! CorruBracket. “The snow guard was a little different,” Gennett says. “It was specifically designed for a corrugated roof.”

The TPO Roof System

The main roof and mechanical well were covered with the TPO roof system, which totaled approximately 8,300 square feet. After Carlisle VapAir Seal725 TR self-adhering air and vapor barrier was applied to the metal deck, crews installed two layers of 2-inch iso. Tapered insulation was applied over the top to ensure proper drainage. The insulation was covered with a 1/2-inch sheetrock and the 60-mil TPO was fully adhered.

Two large smoke hatches manufactured by Bilco were installed over the stage area. The ACDSH smoke hatches measured 66 inches by 144 inches, and are designed for theaters, concert halls and other interior applications that require limiting noise intrusion.

The Installation

The initial focus was to get the roof dried in so work could progress inside the building. The jobsite conditions posed a few challenges. The structure abutted an existing building, and the space was tight. The schedule necessitated multiple trips to the site, which can be a budget-buster on a small project. “We had a lot of trips in and out to accommodate the schedule and get everything dried in so they could meet the interior schedule,” notes Gennett. “We were sort of on call. We made three or four trips out to roof this small project, so it took a lot of coordination because it was completed in pieces.”

Crews tackled the TPO roof sections first. The mechanical well section provided several challenges. Changes in the mechanical well layout necessitated moving some curbs and making adjustments to the tapered insulation. “They were trying to get lot of equipment into a small space,” Gennett explains. “We had to make sure we could get the water to the low spots and route it around all of that equipment. That was probably the biggest challenge on the project.”

Staging material was also problematic, as traffic was heavy and parking space was at a premium. Material was loaded by a crane, which had to be set up in the street. “It’s a postage stamp of a site,” says Gennett. “This is a main thoroughfare, and there is a school right across the street. We had to work around school hours, and we couldn’t be working when the busses were coming in. We usually came in after school started, around 8 a.m., to load materials.”

When it came time to load the metal panels, the cramped jobsite actually paid off. “It was very convenient,” Gennett recalls. “We were able to load the panels onto the adjacent roof and just hand them over. We had a nice staging area for cutting, so all in all it wasn’t bad.”

The corrugated panels were installed with matching edge metal. “It’s not a complicated panel to install, and they look really nice,” Gennett notes. “On the Elm Street side, to the right of the valley was one color, and to the left was another, so we had to match the color with our coping. There were some interesting transitions with our metal. We also had to really pay attention to how the siding was being installed so we could match the metal to the siding and follow the transitions from color to color.”

The perforated wall panels were installed by ProCLAD Inc. of Noblesville, Indiana. “Once the walls were done, we came in and did the transition metal,” Gennett says. “We just had to make sure everything lined up perfectly.”

Planning Ahead

Ensuring a safe jobsite was the top priority for Tecta America Zero and Messer Construction, the general contractor on the project. “Both Messer Construction and Tecta America take safety very seriously. That’s why we’re good partners,” Gennett says. “We had PPE, high-visibility clothing, hard hats, safety glasses for the whole project. All of the guys were required to have their OSHA 10. Anyone outside of the safety barriers had to be tied off 100 percent of the time.”

Planning ahead was the key to establishing the safety plan and meeting the schedule while ensuring a top-quality installation. “This job had a lot of in and out, which is tough in the roofing business,” Gennett says. “But we planned ahead, we made sure everything was ready for us when we mobilized, and we did a good job of coordinating with the other trades. It took a lot of meetings and discussions — just good project management.”

Gennett credits the successful installation to a great team effort between everyone involved, including the general contractor, the subcontractors, and the manufacturers. “We pride ourselves on our great, skilled crews and our great field project management,” he says. “Our superintendents are there every day checking the work and making sure the guys have everything they need. Messer Construction is great to work with, and obviously having the manufacturer involved the project and doing their inspections as well helps ensure the quality meets everyone’s standards and holds the warranty.”

The theater is now another exciting venue in the Over the Rhine neighborhood. “It is really cool spot,” Gennett says. “It’s an up-and-coming neighborhood that’s grown in leaps and bounds in the last seven years. There is a ton going on in Cincinnati. It’s just another part of the city that makes it really fun to go downtown.”

TEAM

Architect: GBBN Architects, Cincinnati, Ohio, www.gbbn.com
General Contractor: Messer Construction, Cincinnati, Ohio, www.messer.com
Roofing Contractor: Tecta America Zero Company, Cincinnati, Ohio, www.tectaamerica.com
Wall Panel Installer: ProCLAD Inc., Noblesville, Indiana, www.procladinc.com

MATERIALS

Metal Roof:
Roof Panels: PAC-CLAD 7/8-inch Corrugated Panels, Petersen Aluminum Corp., www.pac-clad.com
Wall Panels: PAC-CLAD 7/8-inch Corrugated Panels, Petersen Aluminum Corp.
Nail Base: H-Shield NB, Hunter Panels, www.HunterPanels.com
Snow Guards: CorruBracket, S-5!, www.S-5.com
Waterproofing Underlayment: Carlisle WIP 300 HT, Carlisle SynTec, www.CarlisleSyntec.com

TPO Roof:
Membrane: 60-mil grey TPO, Carlisle SynTec
Waterproofing Underlayment: Carlisle WIP 300 HT, Carlisle SynTec
Smoke Hatches: ACDSH Acoustical Smoke Hatch, The Bilco Co., www.Bilco.com

Striking Asphalt Shingle Roof Tops the Restored Music Hall in Cincinnati

Originally designed by Samuel Hannaford in the 19th Century, the Music Hall first opened its doors in 1878. The Music Hall Revitalization Company coordinated the restoration of the 139-year old Cincinnati landmark, which just reopened to the public Oct. 6, 2017.
Photos: CertainTeed

The Cincinnati Music Hall is considered one of the largest and most beautiful concert halls and theaters in the world. It has played host to iconic performances and events for more than a century, from the 1880 Democratic National Convention to performances that helped shape the American arts scene.

A vision and product of 19th century architect Samuel Hannaford, Music Hall—as it’s known across the Queen City—first opened its doors to the public in 1878. Yet the doors on the 225,000-square-foot facility have been closed since May 2016 to allow for a complex interior and exterior restoration effort that would propel the aging building into the modern era while also preserving its beautifully unique characteristics.

The Charge

Restoring the beauty of Hannaford’s showpiece was more than a simple facelift. According to the Music Hall Revitalization Company, the nonprofit coordinating and leading the renovation, engineers investigating the building discovered structural deterioration beyond what one would expect in a 139-year old building, and recommended actions secure the Music Hall’s long-term viability.

The $135 million Music Hall renovation began in the spring of 2016, with the Cincinnati Center City Development Corporation (3CDC) overseeing construction. Following a rigorous request for proposals, 3CDC chose Imbus Roofing to install the new roof.

The Music Hall has been traditionally adorned with high-end shingles, and Grand Manor luxury asphalt shingles from CertainTeed were chosen to replicate the slate aesthetic and stand up to the elements. Photos: CertainTeed

Principal Daniel Imbus and his team were more than up to the task. Not only had Imbus Roofing performed the bulk of the roofing work at Music Hall over the past few decades, they have a rich legacy in the greater Cincinnati area. Among the other high-profile projects with connections to Imbus roofing are the Proctor & Gamble Twin Towers, the Walnut Hills Copper Dome, Paul Brown Stadium and the original Riverfront Stadium.

The team at Imbus worked closely with 3CDC, PWWG Architects and local distributor Midwest Roofing Supply to nail the aesthetic and capture the original essence of Music Hall.

“The roof replacement was a big part of the project, not only for protecting all the interiors that were being restored or replaced, but for the overall look of the building,” Imbus explains. “With the older building and the amount of other work being performed, just getting around the building and scheduling work around other trades such as painting, masonry, HVAC, etc., required a lot of planning.”

The Installation

Imbus partnered with Seth Dorn, branch manager at Midwest Roofing Supply, to find the appropriate materials to for the front towers, Corbett Tower, and Opera House portions of the roof. According to Dorn, the Music Hall has been traditionally adorned with high-end shingles, so they chose Grand Manor luxury asphalt shingles from CertainTeed to replicate the slate aesthetic and endure the wind, rain, snow and other elements typical to Cincinnati. To recreate the distinctive striped pattern of the roof, crews installed approximately 600 squares of Grand Manor shingles in two colors, Stonegate Gray and Brownstone.

The roof’s distinctive striped pattern was recreated with 600 squares of Grand Manor shingles in two colors, Stonegate Gray and Brownstone. Photos: CertainTeed

“We serviced Imbus Roofing with all potential materials for the project,” Dorn notes. “In addition to the shingles, we supplied DiamondDeck and WinterGuard underlayments from CertainTeed to further enforce weather protection.”

A large part of the roof replacement was the Main Hall, which sits above lower sections of the building and has a steep slope. To perform this installation, the Imbus Roofing team had to build scaffolding along the full gutter lines to provide safe and secure roof access and work platforms.

“With the steep slope of the roof, the shingles are an integral part of the exterior look of this historic building,” says Imbus. “It’s an introduction to the amazing interior renovation and exterior restoration.”

The Reopening

The project, more than seven years in the making, was completed on Oct. 1, 2017. The doors officially re-opened on Oct. 6 to kick off a weekend of events that included an opening night gala, a community Open House, and a pair of concerts featuring the Cincinnati Symphony Orchestra.

“It looks awesome,” reflects Dorn. “We will spotlight this job for all of our contractors and customers.”

“We had a great experience with this project,” Imbus adds. “It was a quick schedule with a lot of work to a signature building of Cincinnati. It is great being a part of a successful project that I think will impress everyone in the community.”

TEAM

Developer: Cincinnati Center City Development Corporation (3CDC), Cincinnati, 3CDC.org
Architect: PWWG Architects, Pittsburgh, PWWGgarch.com
Project Coordinator: Music Hall Revitalization Company, Cincinnati, Musichallcincinnati.org
Construction Manager: Messer Construction, Cincinnati, Messer.com
Roofing Contractor: Imbus Roofing, Wilder, Kentucky, Imbusroofing.com
Local Distributor: Midwest Roofing Supply, Cincinnati, Midwestroofingsupply.com

MATERIALS

Steep-Slope Roof System: Grand Manor luxury asphalt shingles, CertainTeed, CertainTeed.com
Underlayments: DiamondDeck and WinterGuard, CertainTeed

Concrete Tile Roofing Protects Canadian Hotel from the Elements

The Moose Hotel & Suites is located in Banff, Alberta, Canada. The resort sits at an elevation of 4,600 to 5,300 feet in the Canadian Rocky Mountains, about 80 miles west of Calgary.

The Moose Hotel & Suites is located in Banff, Alberta, Canada. The resort sits at an elevation of 4,600 to 5,300 feet in the Canadian Rocky Mountains, about 80 miles west of Calgary.

Banff, Alberta, Canada, sits at an elevation of 4,600 to 5,300 feet in the Canadian Rocky Mountains, about 80 miles west of Calgary. The small community (around 8,000 permanent residents) was established as a resort town almost immediately after its hot springs were discovered by Canadian Pacific Railway workers in 1883. The town, which is built in a valley surrounded by mountains, has been a popular tourist destination for more than a century and is known for skiing and, of course, the Banff Upper Hot Springs.

Because of its history of tourism, Banff offers comfortable lodging at every price point. Among the town’s options for accommodations are nine hotels owned and operated by Banff Lodging Co.; the company also has seven restaurants, two spas, and a ski school and rental shop. The Moose Hotel & Suites is the lodging company’s newest four-star property, having opened in July 2016.

Because Banff is a national park, the Moose Hotel & Suites project is significant because it is one of the largest hotel developments (174 rooms) since the Canadian federal government’s 1998 commercial growth cap, which has prevented many hospitality developments from being built. Despite being approved, the Moose Hotel & Suites still was required to adhere to Banff’s design guidelines. The guidelines state they were enacted “to prevent any monstrosities being put there to destroy the general beauty of the park.”

In fact, the guidelines require that all developments, particularly hotels, enhance views to the mountains surrounding Banff. “They want visitors to realize they’re really in the mountains and not just anywhere in a hotel room,” explains Ted Darch, owner of Calgary-based E.J. Darch Architect Ltd., the architect on the Moose Hotel & Suites project. “We wanted to take advantage of the views, so designing the hotel to resemble a village with a courtyard in the middle allowed us to capture the drama of the mountains. You’ll see the reviews on TripAdvisor mention this.”

Darch has been working on Banff Lodging’s projects since the mid-1980s. The concept for the Moose Hotel & Suites evolved over a number of years as Banff Lodging acquired the property for the hotel and Darch worked on other projects for the company. Similarly, Banff Lodging chose the Moose Hotel & Suites’ roofing contractor because of a long-standing relationship.

“We’ve done work with Banff Lodging for about 10 years on most all its other facilities,” explains Brock Hanson, president and CEO of Banff-based Rocky Mountain Sundeck & Roof. “This was a pinnacle Banff job that doesn’t occur often due to the building guidelines. Having this project in our backyard was just fantastic to be a part of.”

Constructed to Withstand the Elements

The new hotel had to meet Banff’s strict design guidelines. It also had to withstand the subarctic climate (winters as cold as -40 F and short and cool summers, as well as 15 to 40 inches of precipitation, typically snow, per year). The Moose Hotel & Suites features spray foam at R-20 in the walls and R-40 in the roof. The spray-foam insulation not only keeps guests and staff warm during Banff ’s long winters, but also protects the building against air and moisture infiltration.

The Moose Hotel & Suites was required to adhere to Banff’s design guidelines, which were developed “to prevent any monstrosities being put there to destroy the general beauty of the park.”

The Moose Hotel & Suites was required to adhere to Banff’s design guidelines, which were developed “to prevent any monstrosities being put there to destroy the general beauty of the park.”


Darch had specified concrete tile roofing on a Banff Lodging hotel previously, but Hanson recommended a new supplier with whom he had previously worked. Darch met with a salesperson from the roofing manufacturer to discuss its concrete tile product. After he checked some samples, Darch was convinced this was the right product for the project.

The distinctive concrete tile was chosen for its energy efficiency and durability. It resembles natural slate to complement the design of the rustic mountain lodge. Because it is concrete, the tile is able to withstand the subarctic region’s extreme weather and withstands flying embers in case of forest fires. “We learned a big lesson about fire recently in Fort McMurray, north of Edmonton, Alberta,” Darch notes. “They had a terrible fire last summer that destroyed something like 2,000 houses. They’re in the forest and Banff is in the forest, so fire resistance was important.”

Concrete Tile Roofing

The tiles’ aesthetic also appealed to Darch; he especially liked that he was able to choose a bright red (Mission Red) for the roof. “From the architectural perspective, what is really nice is the color possibilities and to make the roof color part of the overall scheme of things is great,” he says. “Other roofing options were nice but they didn’t have the snap that the red tile does.”

Photos courtesy of Boral Roofing.

Pages: 1 2

Project Profiles: Hospitality & Entertainment

B.O.B., Grand Rapids, Mich.

Roof Materials

The double-sided green wall surrounds guests with nature and provides fresh ingredients for the food they enjoy.

The double-sided green wall surrounds guests with nature and provides fresh ingredients for the food they enjoy.

The B.O.B.’s 900-square-foot Sky Patio was completed in August 2015 when its signature green wall was installed. The distinctive double-sided green wall surrounds guests with nature and provides fresh ingredients for the food they enjoy.

“Our living wall on the Sky Patio is a vivid symbol of our commitment to sustainability and support of the local environments where our restaurants are located,” says Alice Jasper, director of sustainability, the Gilmore Collection. “It greens up the exterior and interior of the rooftop patio, contributing to the beautification of downtown, making the patio more inviting from the street below and enhancing the dining experience of our guests.”

The two-sided green wall totals 608 square feet. Three exterior sections (48 inches in height) are attached to the outside of the fencing that surrounds the patio. Facing out to the street, these sections frame the Sky Patio on three sides with flowering annuals and perennials. There are five interior sections (45 1/2 inches in height), three on the inside of the perimeter fence, two on the back wall of the building. In addition to flowers, the interior sections include vegetables and herbs used in the kitchen.

The two-sided green wall totals 608 square feet.

The two-sided green wall totals 608 square feet.

“Local sourcing of ingredients is one of our main sustainable hospitality practices,” says Barbie Smith, the Gilmore Collection’s gardener. “With the green wall at the B.O.B., we grow ingredients right near the tables where our guests dine. You cannot get more local than that.”

“What chef wouldn’t want a garden with fresh herbs and produce right in their restaurant? A green wall makes it practical,” adds Mick Rickerd, chef at Bobarino’s. “We utilize the herbs in all our everyday dishes and the vegetables, like Swiss chard and rainbow carrots, in daily features. Our mixology team incorporates fresh basil, mint, lemongrass and thyme into special summer cocktails.”

Green Wall Manufacturer: LiveWall

Roof Report

The B.O.B. is the Gilmore Collection’s most ambitious project, and it exemplifies the company’s commitment to sustainability. The B.O.B. is an acronym for Big Old Building; the 70,000-square-foot, 4-story, red brick building was constructed in 1903 as a grocery warehouse. It stood vacant for decades before the Gilmore Collection saved it from demolition and began its transformation into a landmark hospitality destination in downtown Grand Rapids. The B.O.B. offers multiple venues, including bars, restaurants, comedy and nightclubs, as well as the rooftop Sky Patio, which is accessible through Bobarino’s restaurant on the second floor.

Photos: LiveWall

Pages: 1 2 3 4 5

A Permeable Pavement Patio Outside a Performance Space Features a Distinctive Musical Note Pattern

Since performing its first concert in 1939, the West Michigan Symphony, a professional orchestra in Muskegon, Mich., has been a vital part of the region’s cultural landscape. In spring 2013, the symphony decided it was time to expand its administrative and ticketing services. It moved into offices in the newly renovated Russell Block Building. Located in downtown Muskegon, a block away from the Frauenthal Theater where the orchestra performs its concerts, the historic Russell Block Building was constructed in 1890.

The porous-paving material had to express the musical note motif the landscape architect envisioned for the patio. It is the quintessential design element for the entire rooftop project.

The porous-paving material had to express the musical note motif the landscape architect envisioned for the patio. It is the quintessential design element for the entire rooftop project.

“With the move, the symphony also realized a long-held dream: establishing a flexible space where we could expand educational offerings and stage smaller fine-arts performances,” explains Carla Hill, the symphony’s president and CEO.

Named The Block, the 1,800-square-foot space offers seating on two levels for up to 150. In addition to providing an intimate venue for a variety of arts performances, The Block is available for meetings and special events. The west-facing windows of The Block look out toward Muskegon Lake. However, there was a problem: Outside the windows, an unimproved and unappealing tar roof marred the view.

“In conversations with the symphony and Port City Construction & Development Services, which planned and managed the building renovation, we started envisioning the transformation of the unadorned roof into a rooftop patio and garden,” says Harry Wierenga, landscape architect, Fleis & VandenBrink Inc., Grand Rapids, Mich.

Wierenga designed a 900-square-foot green roof (including 380 square feet of vegetation and a 520-square-foot patio area) as an accessible and appealing outdoor space. His design invites patrons of The Block to the outdoors onto a landscaped rooftop patio.

First Things First

“The existing roof was a tar roof over a concrete deck. Some holes had been boarded over and patched with tar,” notes Gary Post, manager, Port City Construction & Development Services LLC, Muskegon. “If the rooftop patio and garden had not been incorporated into the project, we would not have replaced it. We had to reroof to support the new rooftop outdoor space.”

The Port City Construction & Development Services roofing crew removed the existing roof down to the concrete deck, which they repaired. Two new roof drains were added to improve drainage. A single-ply membrane was selected for the new roof. The crew fully adhered the new membrane to the deck. The crewmembers then installed a geotextile fabric to protect the membrane and rolled out a geotextile drain sheet atop the protection fabric. The drain sheet facilitates drainage to the existing and two added roof drains.

A new 40-inch-high wall around the perimeter shelters the space and enhances rooftop safety. The porous paving’s gray and black custom-color mix harmonizes with the color of the wall.

A new 40-inch-high wall around the perimeter shelters the space and enhances rooftop safety. The porous paving’s gray and black custom-color mix harmonizes with the color of the wall.

A new 40-inch-high wall around the perimeter was constructed to shelter the space and enhance rooftop safety. Preparations also included widening the opening out to the rooftop from the interior of The Block. Glass double doors would be installed to establish a generous and transparent transition from indoors to outdoors.

Permeable Pavement

The project team applied a multi-faceted set of factors in evaluating options and selecting a pavement material for the patio:

  • To eliminate standing water and allow excess stormwater to flow to the drains, the paving material had to be permeable.
  • The plan called for installing the patio and green-roof elements on top of the geotextile drain sheet. The paving material would have to work with the modular green roof selected for the project.
  • The paving material had to be lightweight. By regulation, the maximum static plus live load for the roof is 100 pounds per square foot.
  • For easy access and safety, the pavement had to be low profile to minimize the threshold at the entry into The Block.
  • To create visual interest within the rectangular shape of the roof, the design emphasizes irregular shapes with angles to break up the space. The paving material would have to be flexible to adapt to the design.
  • The musical-note motif Wierenga envisioned for the patio is the quintessential design element for the entire rooftop project. The paving material had to offer the versatility to express the design.
  • Finally, a green-building product was preferred.

The project team considered composite decking and pavers. However, these linear materials were not flexible enough to adapt to the shape of the patio or sufficiently versatile to convey the musical note design.

PHOTOS: Porous Pave Inc.

Pages: 1 2

Project Profiles: Hospitality and Entertainment

Hilton Garden Inn, Cleveland

Team

General Contractor: HOBS Roofing, Canton, Ohio
Roofing Consultant: RS&M, St. Petersburg, Fla.

Because of the area’s harsh winter climate, the hotel’s reroofing project required a redundant roofing system that would be strong and durable. The SOPREMA system chosen is typically used in climates like this for that reason.

Because of the area’s harsh winter climate, the hotel’s reroofing project required a redundant roofing system that would be strong and durable. The SOPREMA system chosen is typically used in climates like this for that reason.

Roof Materials

Because of the area’s harsh winter climate, the hotel’s reroofing project required a redundant roofing system that would be strong and durable. The SOPREMA system chosen is typically used in climates like this for that reason.

Although the selection of this particular roofing system was easy, the installation presented a few challenges. The hotel’s roof includes a cell tower, containing a telecommunication terminal for all of Ohio. The installers had to be careful to avoid interference with the terminal when removing the original roof, as well as applying the new system. In addition, the mortar in some of the walls of the penthouse was deteriorating. The installation team had to flash in the ALSAN RS liquid system to keep water from penetrating and getting into the new roof system.

When the reroofing project began, installers first needed to remove the old coal-tar roof from the structural deck of the concrete building. Next, the deck was primed using Elastocol 500 and then a SOPRALENE 180 SP vapor barrier was heat-applied. This particular vapor barrier is commonly used in northern Ohio when reroofing.

Following the vapor barrier, the installation package was ready to be glued down using DUOTACK, SOPREMA’s low-rise foam adhesive. SOPRABOARD cover board was applied, followed by a layer of heat-applied SOPRALENE Flam 180 and then a heat-applied cap sheet of SOPRALENE Flam 180 FR GR. To finish the project, ALSAN RS 230, a PMMA two-part rapid-curing liquid flashing product, was applied over top in a custom color to match the roof to the aesthetic of the building.

Roof System Manufacturer: SOPREMA

Roof Report

Open since 2002, the Hilton Garden Inn stands 11-stories high and has 240 rooms. The hotel is within walking distance to Progressive Field and the CSU Wolstein Center, and is close to other downtown Cleveland entertainment and dining. The hotel features a business center, pool, fitness center and more. The reroofing project took place in summer 2014.

PHOTO: SOPREMA

Pages: 1 2 3

Clay Tile Roofing Protects a Subdivision’s Clubhouse from the Hot Phoenix Sun while Providing an Old World Look

Located in the Sonoran Desert southeast of Phoenix, the Encanterra Country Club subdivision offers upscale living in houses built by Walnut, Calif.-based Shea Homes and surrounding an 18-hole golf course designed by Tom Lehman. The centerpiece of this vibrant community, however, is the 60,000-square-foot country club known as La Casa, The Club at Encanterra.

The centerpiece of the Encanterra subdivision in Phoenix is the 60,000-square-foot country club known as La Casa, The Club at Encanterra.

The centerpiece of the Encanterra subdivision in Phoenix is the 60,000-square-foot country club known as La Casa, The Club at Encanterra.

Designed to keep the community’s members active and entertained, La Casa, The Club at Encanterra contains four restaurants, a full-service spa, fitness center and three swimming pools. The club features Mediterranean-style architecture to essentially be an extension of the attractive homes in the subdivision.

To achieve a rustic, Old World appearance, Shea Homes specified a two-piece clay tile roof installed in mud set, accented with copper flashings; custom-fabricated ornamental details; and a spray-foam system on the low-slope roof areas. Only a roofing contractor with the experience and capabilities to do all facets would suffice.

Phoenix-based Century Roofing Inc., which has been in business since 1991, has a long history of commercial and custom residential projects. With crews experienced in installing all types of tile, as well as its own metal fabrication shop, the contracting company was chosen to roof the club as it was being built.

Hustling for the Job

Steve Schwoerer, president of Century Roofing, knows what it takes to hustle and land large jobs, like La Casa, the Club at Encanterra. Knowing the project was going to be a landmark building in the valley attracted him to it. “We got it off the permit list, pursued it, bid on it and landed it, although not quite so cut and dry,” he says. “We have a lot of custom-home
experience and in Phoenix that means clay tile roof experience, so it fit in perfectly with our abilities.”

Originally, the club’s designer specified a different type of clay tile than what was actually installed on the roof. However, Schwoerer invited Irvine, Calif.-based Boral Roofing to come up with a color match and submit a quote for its tile to be installed on the project. “Boral had their plant manager fly into Phoenix to look at the roofing on the existing guard house that Shea Homes was trying to match,” Schwoerer recalls. “Boral then formulated a custom-blended tile and shipped the tile to Phoenix so a mock-up could be done for the architect’s approval, which they received.”

In addition to its curb appeal, the tile offered other benefits. Manufactured from naturally occurring geologic material (59 percent of which is recycled content), Boral clay tiles have received Cradle to Cradle Gold certification from the Cradle to Cradle Products Innovation Institute, San Francisco. The certification program assesses products in five categories: material health, material reutilization, renewable energy and carbon management, water stewardship and social fairness. The tile product is wind, hail and fire resistant, as well as considered a cool roof, meaning it reflects heat from the sun, which reduces the need for air conditioning and provides savings on energy bills.

To achieve a rustic, Old World appearance, Shea Homes specified a two-piece clay tile roof installed in mud set, accented with copper flashings

To achieve a rustic, Old World appearance, Shea Homes specified a two-piece clay tile roof installed in mud set, accented with copper flashings

Working in Phases

The roofing work was completed in phases as La Casa, The Club at Encanterra was being built. “Anytime you do a project of this size, the general contractor has scheduling demands that add to the difficulty, especially when you’re working in stages and
they want you out there as it’s being built rather than all at once,” Schwoerer states. “Their version of what’s roof-ready versus what’s actually roof-ready is one of many things that causes a roofing contractor stress!”

Century Roofing’s five-man crew began by installing the spray-foam roof on the low-slope portions of the building, which compose 130 squares of the total roof area. Although spray-foam roofs in Arizona typically are 1-inch thick, the club’s roof is 2-inches thick to achieve additional R-value. The foam was sprayed directly onto the wood deck and two base coats were applied before the final topcoat, which features a #9 crushed marble cast into the wet topcoat by hand.

PHOTOS: US TILE BY BORAL

Pages: 1 2

Projects: Hospitality & Entertainment

The Lobby, Gerald R. Ford Amphitheater, Vail, Colo.

The Lobby, Gerald R. Ford Amphitheater, Vail, Colo.

The Lobby, Gerald R. Ford Amphitheater, Vail, Colo.

Team

Design Architect: Zehren & Associates, Avon, Colo.
Engineer: Monroe & Newell Engineers Inc., Denver
Owner: Vail Valley Foundation, Vail

Roof Materials

The Vail Valley Foundation envisioned an iconic entrance for the amphitheater that not only would accommodate guests, protect against the elements and provide facilities, but also would recognize and celebrate the Ford family and mirror the amphitheater’s atmosphere.

Under the Vail Valley Foundation, Zehren’s team of architects chose approximately 5,500 square feet of PTFE fiberglass membrane canopies to make the vision for The Lobby a reality. PTFE, or polytetrafluoroethylene, is a Teflon-coated woven fiberglass membrane that is durable and weather resistant. The PTFE fiber coating is chemically inert, capable of withstanding extreme temperatures and immune to UV radiation.

Designer, fabricator and installer of PTFE fiberglass membrane: Birdair

Building Report

The Gerald R. Ford Amphitheater is a remarkable outdoor venue nestled along a hillside with a stunning view of the Rocky Mountains. The Lobby, which is adjacent to the Betty Ford Alpine Gardens and Ford Park, serves not only as an impressive entrance to the amphitheater, but also as a shelter from inclement weather, a social gathering point prior to entering the amphitheater, and a place for ticket and bag check. The Lobby allows for a smooth transition into the venue.

Within the Lobby resides a mini-stage that can accommodate pre-show performances, along with a new stand for concessions and restrooms. Around the perimeter of the space rests informal boulder seating, and alpine landscapes border the surrounding walls. Overall, the aesthetics of the space mirror the pristine landscape and enjoyable outdoor atmosphere.

The Lobby also holds a Ford family tribute: a series of symbolic sculptures and interpretive elements intended to pay homage to President and Mrs. Ford and their family. This tribute is a new landmark in Vail celebrating the family’s commitment to their adopted hometown and the positive changes that they made to the community.

PHOTO: BIRDAIR