Contractor Conquers Tough Weather, Tight Schedule

The roof on the new Goodman Logistics Center (the building on the right) encompasses more than 1 million square feet. The roof system installation met an aggressive timeline that spanned the winter months. Photo: Goodman Carlisle LLC

The roof on the new Goodman Logistics Center (the building on the right) encompasses more than 1 million square feet. The roof system installation met an aggressive timeline that spanned the winter months. Photo: Goodman Carlisle LLC

Goodman, an international commercial and industrial property group, approached Donald B. Smith Inc. of DBS Roofing in November 2017 to support the roofing of the company’s new Logistics Center in central Pennsylvania.

Founded in 1948, DBS Roofing is a second-generation, privately held company whose principles of quality and workmanship have earned the team countless awards. Among those honors include the Firestone Master Contractor recognition, the Baltimore Builder’s Exchange “Craftsman of the Year Award” and numerous industry publication recognitions for notable projects.

The Logistics Center roof was 1,010,000 square feet and was established on a very aggressive timeline that spanned through the tough Northeast winter months. The initial specifications of the job called for a mechanically fastened TPO roof system, which was going to be challenging with the size and timeline of the project. Additionally, the condensation levels in central Pennsylvania are not ideal for mechanically fastened solutions, as it would require applying a vapor barrier and foam around all perimeters, exceeding the original budget and schedule.

To save time and keep the project moving forward during the unfavorable winter conditions, DBS Roofing elected to use one of the company’s favorite “box world” solutions — Firestone Building Products (FSBP) UltraPly TPO SA with Secure Bond Technology.

Photo: Goodman Carlisle LLC

The TPO roofing system is comprised of a self-adhering membrane with factory applied, pressure sensitive adhesive and technology designed to ensure uniform adhesion coverage across the entire membrane. According to the manufacturer, the system can be installed in weather as cold as 20 degrees Fahrenheit.

“Commercial roofing in central Pennsylvania can be very challenging during the winter season, but Firestone UltraPly TPO SA allows our business to continue working through those conditions and prosper,” says Donnie Sanders, president of construction, DBS Roofing. “Being able to apply the Firestone TPO SA at 20 degrees resulted in a successful year for us.”

The Goodman Logistics Center roofing project began on November 1, 2017 and was completed on time March 1, 2018.

TEAM

Roofing Contractor: Donald B. Smith Roofing Inc., Hanover, Pennsylvania, www.dbsroofing.com
General Contractor: ARCO Design/Build Northeast, King Of Prussia, Pennsylvania, http://arcodbi.com

MATERIALS

Membrane: UltraPly TPO SA with Secure Bond Technology, Firestone Building Products, www.firestonebpco.com
Insulation: 2.5-inch ISO, Firestone Building Products