Projects: Historic Preservation

KANSAS STATEHOUSE COPPER DOME & ROOF REPLACEMENTKANSAS STATEHOUSE COPPER DOME & ROOF REPLACEMENT

KANSAS STATEHOUSE COPPER DOME & ROOF REPLACEMENT, TOPEKA, KAN.

KANSAS STATEHOUSE COPPER DOME & ROOF REPLACEMENT

KANSAS STATEHOUSE COPPER DOME & ROOF REPLACEMENT

TEAM

SHEET-METAL CONTRACTOR (DOME): Baker Roofing Co., Raleigh, N.C.
SHEET-METAL CONTRACTOR (ROOF): MG McGrath Inc., Maplewood, Minn.
SPECIALTY FABRICATION (DOME): Ornametals LLC, Decatur, Ala.
ARCHITECT: Treanor Architects P.A., Topeka
GENERAL CONTRACTOR: J.E. Dunn Construction Co., Topeka

ROOF MATERIALS

The $22 million copper roof and dome replacement, completed in late December 2013, occurred over previously restored, occupied spaces and utilized approximately 127,000 pounds of copper. The east and west wing roofs are covered with 24,700 square feet of 20-ounce copper batten-seam roofing. The central, north and south wing roofs are finished with a hybrid horizontal and standing-seam roof constructed of 20-ounce copper to replicate the historic roof.

ROOF REPORT

The Kansas Statehouse’s copper dome, contrasted by the limestone structure, has captured the attention of citizens and visitors alike for more than 100 years. Built in three distinct phases during a 37-year period, the Kansas Statehouse reflects the changes in construction between the 1860s and the turn of the 20th century.

Planning for the statehouse’s restoration began in 1999 with an overall evaluation of the building and schematic design. For the legislature to continuously occupy the building, the construction was broken into six major phases and 29 separate bid packages. As part of the statehouse preservation and restoration, Treanor Architects completed a study on the existing roof and dome systems between 2007-10 and concluded the entire copper cladding needed to be replaced. Because of its longevity, copper proved to be the best long-term value for the project when other cost factors, such as access, associated repairs and maintenance, were taken into consideration.

TO COMPLY with the Secretary of the Interior’s Standards for Rehabilitation, the replacement copper design had to replicate the historic construction as closely as possible. However, areas identified as leak-prone or lacking in provision for thermal expansion were targeted for changes to better protect the building in the future. The design included repairs for substrate damaged by infiltration and alterations to the substrate to accommodate copper detail changes. The original copper installations lacked underlayment. To minimize changes in the manner that the roof envelope behaves, breathable underlayment was used to the greatest extent possible.

Approximately 127,000 pounds of copper were recycled and portions of the copper were salvaged for reuse in the Kansas Statehouse’s new visitor center. MG McGrath performed the fabrication and installation of 65,250 square feet of sheet metal on the roof. Low-slope areas of the central roof, which were originally clad with standing seam, were re-clad with 20-ounce soldered flat-seam copper to provide a more watertight roof. To meet the aggressive schedule, roofs were sequenced to allow for tear off and substrate repairs to occur while sheet-metal installation crews worked on another roof.

DETERIORATED SUBSTRATE required repairing structural framing and the wood and masonry decks. Work on the 21,300 square foot dome was performed by Baker Roofing with custom fabrication of the ornamental trim and windows performed by Ornametals. A 365-foot-tall, free-standing tower crane was used to deliver materials and equipment. Crews worked in a spiraling pattern from the bottom of the dome up to sequence tear-off, substrate repairs and sheet-metal installation.

Standing-seam 20-ounce copper cladding was used for radius components at the base and top of the dome. The distinctive horizontal seamed panels used in the original construction were replicated in 20-ounce copper, and templates were created for each panel to account for differences in the compound curvature and spacing of the attachment points. In total, the dome required 230 linear feet of built-in monumental gutter constructed from 32-ounce copper and 752 linear feet of 24-ounce copper rib moulding.

PHOTOS: ARCHITECTURAL FOTOGRAPHICS/TREANOR ARCHITECTS

Be the first to comment on "Projects: Historic Preservation"

Leave a Reply