PHOTO 2: Moisture intrusion at the base of this wall was the result of water circumventing the through-wall flashing
and roof base flashing termination seen in Photo 1. A big concern with conditions, such as this, is the propensity of the materials to promote mold growth.<\/p><\/div><\/p>\n
The exposed brick above the termination bar and below the stain- less-steel drip of the through-wall flashing is susceptible to water flowing down the surface of the brick. Water passing through the brick above is supposed to be weeped out; however, at the exposed brick above the termination bar, the water moves into the wall and has nowhere to go but inward.<\/p>\n
The cost to repair these conditions can be, depending on the conditions, expensive. Repairs often require brick removal and through-wall flashing mitigation. In this particular case, be- cause there is a stainless-steel drip, my team recommended a stainless-steel counterflashing be pop-riveted to the drip and extended over the termination bar.<\/p>\n
Why is the interface of roof base flashing and masonry through-wall systems so difficult for architects and roof consultants to detail? I believe it is because they have no clue it needs to be detailed as an interface, especially because detailing of appropriate through-wall systems is so sporadic. I endeavor in this article to change at least the knowledge part.<\/p>\n
The detailing of this condition not only requires the ability to interface two building systems, but also requires considerable time to ensure specification of wall sectional details and roofing details are appropriately placed where the responsible trades will see them.<\/p>\n
PHOTO 3: Still under construction, the stainless-steel counterflashing has
been installed. The roof base flashing will terminate below the stainless-steel counterflashing receiver. Hutch prefers brick below the through-wall flashing and above the roof deck, though the masonry mortar joints below the through-wall flashing should have been struck flush.<\/p><\/div>\n
NEW CONSTRUCTION<\/h4>\n
New construction provides us a clean slate to \u201cdo it right the first time\u201d. The first order of business is to determine the height of the base flashing. This can be tricky with tapered insulation and slope structures with saddles. Let\u2019s consider the following examples (see Detail 4, page 3):<\/p>\n
EXAMPLE 1<\/strong>
\nWe are dealing with a flat roof, tapered insulation, cover board and bead-foam insulation in ASHRAE Climate Zone 5, which has an R-30 minimum.<\/p>\n\n- The roof drain is 32-feet away from the wall. Code requires 5.2 inches of insulation at 4 feet from the drain, so let\u2019s assume 5 inches at the drain.<\/li>\n
- 1\/4-inch tapered starts at 1\/2 inch at 32 feet. That\u2019s 8 inches, plus the starting thickness of 1\/2 inch, which equals 8 1\/2 inches.<\/li>\n
- Cover-board thickness is 1\/2 inch.<\/li>\n
- Bead foam thickness is 3\/16 inch for each layer. Let\u2019s assume five layers, so 1 foot of bead foam.<\/li>\n
Thus, the surface of the roof at the wall will be 15 inches above the roof deck.\n<\/ul>\n
Because you would like to work at the masonry coursing level and given that concrete masonry units (CMU) are nominal 8 inches, you are looking at placing the through-wall flashing 24 inches above the roof deck.<\/p>\n
This 24-inch dimension of where to place the through-wall flashing needs to be placed on the building section and\/or wall section because the mason, which will be onsite prior to the roofing contractor, will need to know this information.<\/p>\n
This 24-inch height begs another termination question: What occurs at the roof edge with this height? Hold that thought for now. Terminations at intersections will be discussed in future articles.
\n
\n
PHOTO 4: Instead of the construction in Photo 3, here, concrete masonry units were installed below the counterflashing receiver. If ever exposed, CMU will readily take on water. CMU walls also can excessively absorb adhesives and two applications are recommended.<\/p><\/div>EXAMPLE 2<\/strong>
\nThis time, we\u2019re dealing with a structurally sloped roof deck at 1\/4 inch per foot toward centrally located roof drains. The roof width is 48 feet. Tapered insulation saddles between roof drains set 24 feet off the masonry wall. The roof is composed of cover board and bead-foam insulation. This is ASHRAE Climate Zone 5, which has an R-30 minimum.<\/p>\n\n- To meet code, thermal insulation totaling 5.2 is required. I suggest that this be in multiple layers, say 5 inches.<\/li>\n
- With the drain being 24 feet from the wall, tapered insulation saddles will need to be 16 feet in width at 1\/2-inch-per-foot slope (saddles need to slope twice the main slope to be effective). Thus, tapered at 1\/2 inch per foot for 8 feet is 4 inches, plus the 1\/2 inch starting thickness. Total thickness is 4 1\/2 inches of ta- pered insulation at the ridge.<\/li>\n
- Cover-board thickness is 1\/2 inch.<\/li>\n
- Bead-foam thickness is 3\/16 inch for each layer. Let\u2019s assume three layers, so about 5\/8 inch.<\/li>\n
\u00bb The roof deck will drop 6 inches from the roof edge to the low point.
\n\u00bb The height of the flat and tapered-insulation saddle at the wall is 10 5\/8 inches; we\u2019ll say 11 inches, which will be approximately level with the roof edge with its 5 inches of insulation.\n<\/ul>\n
The through-wall flashing should be at \u00b119 inches (11 inches of insulation plus 8 inches for roof base flashing) above the low point of the roof deck. The exact dimension needs to be worked out in the wall section.<\/p>\n
As noted with the previous example, the location and height of the through-wall flashing should be placed on the building section and\/or wall section because the mason, which will be on- site prior to the roofing contractor, will need to know this information.
PHOTO 5: Twenty years ago, Hutch had to be creative when the through-wall flashing could not be raised and the roof surface rose above the wall flashing. In this photo, an interior gutter (with roof drains) was designed at the base of the wall below the through-wall flashing. It has performed well for decades.<\/p><\/div><\/p>\n
With the required height for the through-wall flashing, based on the roof insulation, one can begin to detail the roof to masonry wall. For our discussion, we will assume the roofing is a single-ply membrane. The first challenge is to draft the condition correctly: roof deck location, support structure, angle at the wall, wall components, appropriate cavity spaces, wall insulation (should run down below the roof deck).<\/p>\n
Thinking about how the wall and roof will be constructed, the sequencing is helpful. If you are not familiar with the construction of buildings, get yourself out in the field, watch and learn.<\/p>\n
Following are key components of the detail to be shown:<\/p>\n
Draft the detail at a minimum of 3 inches equal to 1 foot. Anything smaller will not allow for the appropriate level of detail to be shown.<\/p>\n
\n- Through-wall flashing membrane is a soft, flexible material and prone to sagging if not supported at wall cavities. Thus, the wall cavity will need to be a bridge with the metal counterflashing material or closed with insulation.<\/li>\n
- The counterflashing material should be compatible with the mortar and lime. Anodized aluminum and galvanized steel have the potential to corrode. Stainless steel and copper traditionally have been used.<\/li>\n
- The metal gauge needs to be thick enough to offer strength and thin enough to allow for multiple bends. <\/li>\n
- Show the counterflashing receiver set in continuous butyl sealant on the masonry.<\/li>\n
\u00bb In the sheet-metal and flashing section, specify the fabrication of the counterflashing receiver and provide it to the masonry contractor for installation.
\n\u00bb In the masonry section, specify that the mason is to install the counterflashing receiver provided by others.
\n\tNote that the mason is to provide needed dimensions, especially if the receiver is covering a cavity.
PHOTO 6: Four inches of additional insulation are going to be added to this existing roof, which Hutch designed 25 years ago. The new insulation will require raising the interface of roof base flashing and masonry through-wall systems.<\/p><\/div><\/p>\n
- The through-wall flashing material, if not sheet metal, is recommended to be a self-adhering membrane.<\/li>\n
\u00bb I suggest that not only should the specification call for priming of the substrate, but also that this be noted on the detail.<\/p>\n
- The through-wall flashing membrane should extend back to the masonry back up, be formed tight in the corner, extended up and over the CMU block above\u2014typically 8 inches\u2014and extended at least 3 inches back on the horizontal.<\/li>\n
- Through-wall flashing laps: Experience shows us that laps can open, typically because they do not get primed and they are not mated tightly into corners. Thus, we require all laps be primed and a 6-inch cover strip of flashing material be applied, the edges of which are caulked.<\/li>\n
- Premolded interior and exterior corners are recommended over field-fabricated because of the varying level of workmanship in the field.<\/li>\n
- To weep the wall, I recommend cell vents instead of cotton ropes, which calcify over time. The cell vents should be shown atop the through- wall flashing, not atop a bed layer of mortar.<\/li>\n
- If the mason contractor is on the ball and the roofing contractor willing, some membrane base flashings can be placed below the through-wall flashing and \u201chung\u201d to be tied into the new roof system to eliminate the termination bar.<\/li>\n<\/ul>\n
\n