Complex Reroofing Project Restores Jacksonville’s Historic City Hall

Many roofing contractors will tell you that the easiest part of any project is the actual roofing work. This is particularly true of projects that have challenging administrative, safety, and/or installation requirements.

However, when it came to reroofing the historic St. James Building in Jacksonville, Florida, which serves as City Hall, it was doubly challenging for McCurdy-Walden, Inc., a full-service commercial roofing and waterproofing contracting company based in the city. A variety of factors made this project especially challenging and complicated, including the building’s location and multiple roof levels, access to the roof, staging of the roofing materials, parking for the crew, coordinating the work with City Hall, as well as managing the intense safety and administrative requirements.

The building, designed by famed architect John Klutho, originally opened in 1912. In the late 1990s, the 342,000-square-foot facility underwent a complete renovation to bring the facility up to current standards and code requirements to restore many of the unique architectural details and match the original stone on the exterior façade. Today, the building is registered in the National Register of Historic Places. It not only serves as Jacksonville’s City Hall — it also provides office and meeting space for many of Jacksonville’s Public Works Departments.

“Unfortunately, we were made aware of some of the more extensive administrative requirements for this project after we were awarded the contract and sitting at the pre-construction meeting,” says Jonathan Walden, chief operations officer for McCurdy-Walden, Inc. “The administrative portion of the project turned out to be pretty challenging in itself. It involved city officials, their security team, a site-specific safety plan, hazard assessment report, evacuation procedures, rally points, and multiple points of egress, and all the men were trained on each procedure and knew what to do, where to go at any given point during the project.”

Safety First

Photos: Carlisle SynTec

Every one of McCurdy-Walden’s crew, as well as every subcontractor who went onto the roof, had to be fingerprinted and undergo a background check before they could access the facility or the roof. Once approved, each person was provided a badge for the project and still had to go through a security checkpoint to access the roof.

To expedite daily access to the roof, McCurdy-Walden set up exterior stair scaffolding from the street level, which included a covered sidewalk area for foot traffic. The crews still had to check in with security, but access to the roof was faster and they didn’t have to walk through City Hall.

Another major hurdle for the project was the extensive site safety and evacuation plan. The roofing contractor had to develop an emergency evacuation plan with two egress routes, and meeting points from all sides of the building.

If all of that was not challenging enough for McCurdy-Walden, the building consumes an entire block in the heart of the busy city, so loading and unloading the roof also posed challenges.

“We had to use a large 80-ton crane to get all the roofing materials and equipment to the roof,” says Jaime Yanez, project superintendent for McCurdy-Walden. “To do that, we started working at 3 a.m., and we shut down an entire street for the day. We had four police officers onsite that day redirecting foot and car traffic.”

Roofing Challenges

The 69,000-square-foot roof is divided into several sections and eight different levels, one of which was a mere 25 square feet. The building has a parapet wall, with a 5-foot ledge around the outside of the building. The old roof was a two-ply modified bitumen system with a cap over 2-inch wood fiber insulation. The roof was over 20 years old, blistering, and at the end of its useful service life. Most of the project was a re-cover; however, McCurdy-Walden also had to remove and replace about 2,800 square feet of wet insulation with varying thicknesses and tear out and reinstall 8-foot-by-8-foot sumps at every drain.

The roof was originally specified as an 80-mil white PVC membrane, but McCurdy-Walden recommended Carlisle’s gray Sure-Flex PVC membrane with patented APEEL Protective Film for the project. “We felt that the gray material would be better than the white for a few reasons,” says Walden. “The glare from a white roof would be pretty bad for the surrounding buildings, so we suggested the gray, which we believe will not look as dirty over time. And we really love the way the APEEL product keeps the roof so clean during installation.”

Carlisle’s patented APEEL is a protective film on the surface of the membrane that protects it from scuffs and dirt accumulation during installation. The film is easy to remove, improves the aesthetics of the finished roof, and can save valuable time and labor by eliminating the need to clean the roof after the installation is completed.

For the new roof, the crew from McCurdy-Walden first cleaned and vacuumed the roof to remove all the loose dirt and debris that had accumulated over the years. Then they fully adhered a half-inch high density cover board over the existing modified bitumen roof using Carlisle’s VOC-free Flexible FAST Adhesive, a two-component, low-rise polyurethane adhesive designed for bonding membrane or insulation to various substrates.

“Flexible FAST provides an additional R-value of 0.20 to 0.50 per layer,” says Walden. “According to the National Roofing Contractors Association, up to 10% of R-value can be lost on the roof due to joints in the insulation, but the expanding nature of Flexible FAST Adhesive helps to seal insulation joints to maintain a consistent R-value, which is important here in Florida.”

On the wet areas of the roof, the crew completely removed the old roof and insulation down to the deck, which was part concrete and part steel. The deck was approximately 4.5 inches below the plane of the existing roof, so McCurdy-Walden installed two layers of 2-inch polyiso and the half-inch cover board to bring the roof to the proper height. Once that was finished, they fully adhered the 80-mil Carlisle Sure-Flex PVC membrane using Carlisle’s CAV-GRIP PVC Adhesive, an aerosol contact adhesive used to adhere the membrane to both horizontal and vertical services.

Flashing Details

There was also extensive flashing and detailing work on the roof. In addition to the numerous penetrations including vent pipes, exhaust fans, and a large chiller, there was a stairwell and several curbs to flash, and many new pitch pockets to install, not to mention the 75-foot octagonal dome on a 5-foot-tall stucco wall in the center of the building, which had to be re-flashed.

“The glass dome is an iconic centerpiece of the building’s design. It sits directly over the building’s central lobby,” notes Yanez. “We had to remove all the glass panels, clean the glass and metal framework, including the horizontal structural joints, re-seal each panel, and ensure that weep holes were all open and functioning properly. Not only was it a ton of work, but whenever our team was working on the dome, we had to have the lobby closed to all foot traffic for safety. That was a big inconvenience for City Hall, and we had to push the dome work back several times to accommodate the city’s schedule. But in the end, our guys got it done and did it safely. It came out great.”

Then there was the electrical work, including a series of light posts on top of the perimeter wall and flagpoles with lights mounted to the roof that illuminate the flags at night. The building’s lightning protection system had to be removed at the outset of the project and then re-installed and re-certified at the end.

The last bit of roofing work was the 4-foot-wide perimeter outside of the parapet wall. For this portion of the roof, the crew mechanically fastened the half-inch cover board, and then fully adhered the membrane using CAV-GRIP. The membrane was then flashed to the side of the structure with a termination bar covered by surface-mount metal and terminated at the drip edge with Carlisle’s SecurEdge 2000 Extruded Drip Edge and SecurEdge 2000 Fascia system, which were also installed on top of the parapet wall and on the edges of all the higher portions of the roof.

“The crew were all in harnesses with lifelines secured around the 4-foot brick and concrete bases of the lampposts,” says Yanez. “We had a few workers out on the ledge installing the roof, including a safety spotter, and then several others helping them from the roof side of the wall, providing materials and support. We also had a safety monitor on the sidewalk below whenever our crew was working on that part of the roof. We had to do this work over the weekend and during off hours when there was little or no traffic in the area. It was probably the most nerve-wracking portion of the project.”

The final step was to peel the APEEL Protective Film off the membrane. The film came off quickly and easily to reveal the very clean new roof.

In the end, the City of Jacksonville was very happy with the project. The APEEL kept the membrane looking clean and new, and everyone was very impressed with the magnitude of the challenging work by McCurdy-Walden.

TEAM

Roofing Contractor: McCurdy-Walden, Inc., Jacksonville, Florida, mccurdywalden.com

MATERIALS

Membrane: 80-mil Gray Sure-Flex PVC with APEEL Protective Film, Carlisle SynTec, carlislesyntec.com

Be the first to comment on "Complex Reroofing Project Restores Jacksonville’s Historic City Hall"

Leave a Reply